18-unit air conditioning install, Round Spinney
A large commercial air-conditioning installation for Crest Scaffolding: 15 indoor units and 3 outdoor units, linked by miles of insulated refrigerant pipework, with every unit wired and isolated.

The brief
The new Crest Scaffolding office building needed heating and cooling in every room, from private offices to the conference room.
That meant 15 indoor units served by 3 outdoor units, a far bigger system than a typical home or small office install.

Electrical work
- 01
Indoor units
15 indoor units installed across the building so each space has its own comfort control.
- 02
Outdoor units
3 outdoor units set out side by side along the building, each with its own rotary isolator.
- 03
Pipework
Miles of refrigerant pipework run from every indoor unit back to the outdoor units, then carried neatly along the wall on tray.
- 04
Electrics
Power supplies, isolation and controls wired to every unit as part of our electrical installation.
Challenges on site
The sheer length of pipe
Getting miles of pipework through the building to 15 indoor units took careful route planning before the ceilings closed.
Insulating every length
Every metre of refrigerant pipe had to be insulated, which is slow, careful work at this scale but essential for efficiency.
The result
A complete 18-unit system giving the whole office building year-round heating and cooling.